The CCSD Stadium project is located at 1000 Warrior Way, Mt. Pleasant, SC 29466.

Project Manager: Bart Bodkin 

Architect: McMillan Pazdan Smith Architecture 

Owner: Charleston County School District

Project Overview:

The project consists of a new design-build athletic stadium at Wando High School.

 

End of April/May Project Updates

4/30

Home concourse masonry is ongoing

Pressbox masonry is ongoing

Home concourse & pressbox steel has started

Field House masonry has started

Visitor’s bleacher foundations are ongoing

Visitor’s concession building slab prep is ongoing

Field preparation for turf contractor mobilization is ongoing

April Project Updates

4/13
Home concourse slabs-on-grade are complete
Home building 308 vertical CMU is ongoing
Field house slab-on-grade is complete
Elevator pit waterproofing is nearly complete
Visitor's bleacher foundations have started 
Visitor's concession building slab prep has started
Field preparation for turf contractor mobilization is ongoing 

 

March Project Updates

3/26
Field house and home concourse plumbing rough-in ongoing
Elevator pit waterproofing and concrete are ongoing
Storm drainage nearly complete
Pressbox foundation and elevator pit to be poured this week 
3/19
Home concourse building foundations to finish this week
Field house masonry stem walls complete
Plumber roughing in under home concourse slabs
Storm drainage should be 95% complete the week of 3/19

Previous Project Updates

Water and sewer on-going 
Field house foundations started
1/3 of the footings poured
Prepare the concrete, storm drain and sewer
Site Demo
Underground Utilities 
Earthquake drains and sewer installed
Sitework on-going
 

CCSD Stadium