The K. Hovnanian's Four Seasons at Lake of Cane Bay projects are located at 322 Cane Bay Boulevard, Summerville, SC.

Project Manager: Ron Jaruzel  | Superintendent: Joey Baker

Architect: Fieldstone Architecture & Engineering 

Owner: K. Hovnanian's Four Seasons at Lakes of Cane Bay, L.L.C.

Project Overview:

The project consists of the Gatehouse, Entrance Monuments, Clubhouse Sitework, and Pools.

 

May 

Week of 5/20

Clubhouse: Exterior Siding is complete, wall and ceiling inspections are complete in A & B, Scaffolding is being erected in Natatorium, Wall insulation to start next week, drywall to start soon.

Pool & Tennis Buildings: Building pads are tested, concrete crew to mobilize next week to start foundations.

Hardscapes/pool/dock: Dock pilings and tie backs are installed, site grading for hardscape has started, roof drain leaders are tied in, water is  turned on. Pool construction to resume early June

April

Week of 4/30

Exterior siding to be completed this week at Natatorium.

Interior rough-in of electrical and mechanical trades on-going.

Fire Sprinkler piping was delivered and rough-in has started.

Layout of Pool Cabana/Tennis building to be completed. Building pads to be done this week.

Site conduit install on-going.

Materials for dock bulkhead were delivered.

Week of 4/23

Exterior siding to be completed this week.

Interior rough-in of electrical and mechanical trades on-going.

Fire protection system installation to start this week.

Exterior pool piping was passed and backfilled, kiddie pool work to resume in early May.

Water meters have been set, site water is in service.

Drawing revisions received.

Layout of Pool Cabana/Tennis building to be completed.

Site conduit install on-going.

Week of 4/16

Exterior pool piping is being tested, kiddie pool is being excavated 

Waiting on drawing updates for A drawings, on-going change order coordination with the owner

Owner provided notice to proceed on Pool Cabana & Tennis Buildings 

Exterior siding and ISO is ongoing at Building C

 

March

Exterior siding is ongoing at Building C
Interior rough-in of electrical and mechanical trades on-going
Exterior pool piping rough-in is on-going 
Waiting on drawing updates to proceed with ordering materials 
Storm water revisions were completed 
ISO insulation on walls to start week of 4/2 at Natatorium 

 

January/February

Storm revisions are on-going
Siding is continuing on exterior
Exterior siding and trim has started 
MEP rough-in is on-going throughout the building 
Outdoor pool construction is underway