The KICA Sandcastle project is located at 1 Shipwatch Road, Kiawah Island, SC 29455.

Project Manager: Don Houghton | Superintendent: Joel Dean

Architect: Bello Garris Architects 

Owner: Kiawah Island Community Association 

Project Overview:

The project consists of a renovation to the existing Sandcastle Community Center Building, along with the construction of a new pool and bath house. The work in the existing building is limited primarily to updating the existing finishes and fixtures. The new bath house facility will be located above the base flood elevation and meets the restroom requirements resulting from the new pool and deck area. The existing outdoor bar facility is being converted to unconditioned storage space and the bar is being relocated to the porch of the existing community center building. 

 

April Project Updates

Week of 4/30

Pool CMU Walls are 75%complete. 

Exterior Tabby shell Stucco on exterior of building is 75%.  Ongoing at the Outdoor Bar Area

IPE Shade Structure over Outdoor bar is 80% complete. 

Interior Paint is 80% complete

Light fixtures are being set throughout

 

March Project Updates

Helical Pile are commencing the week of 3/19
2nd floor and 1st floor deck framing is underway
Interior walls are being sanded and finished 
Double doors along South Elevation will be installed by the end of week 3/19
Kitchen FRP Panels are being installed 
 

January/February Project Updates

 
Exterior paint is at 70% completion  Deck framing issues to be resolved this week 3/12
Interior curtain wall steel erection Kitchen remodel to be completed 
Re-roofing scope to be complete this month  Curtain wall to be framed 
Bathroom tile completion on 1st and 2nd floor  IPE decking replacement in select area to be completed 
Sitework clearing for the new pool Helical pile scope complete and pool grade beams to be near complete 
Helical piles to be completed for the pool